Taipa Pump Station Update

Work on the new Taipa sewage pump station continues.  The work now focuses on excavation to build the structure housing the 3 pumps. 

The excavation is approximately 12 meters deep and 25 by 12 meters wide. Later in the project work will begin on the connection pipe networks, revamping and upgrading the existing network.

pump-station-1

Design Services – Welcoming New Challenges

Pengest Internacional has revamped and increased its design team. We can now offer more dedicated and improved design services to our clients. We offer a full spectrum of engineering planning, design, and construction management services, from planning and permitting through preliminary and detailed design to start-up and commissioning for all types of projects.

Our experts are skilled at leading and executing successful, multidisciplinary projects. We are experienced in the coordination of projects with strict management of quality, value, schedule and cost. Our engineering and design services range from planning and permitting through preliminary and detailed design to start-up and commissioning for all types of projects.

New Contract awarded to Pengest Internacional

Pengest is proud to announce that we have been awarded a contract for supervision and construction management for the new bridge connection Macau to Zone A reclamation.

With a history of 3 bridges successfully completed in Macau, Pengest Internacional has been yet again entrusted by the Macau Government to assist in the completion of this important project for the future development of Macau.

The project consists in 2 parallel bridges stretching over the water, linking Hac Sa Wan, Macau to the north most point of the Zone A reclamation area. The project also includes an vehicle overpass and a pedestrian underpass along the breakwater.

map

Multi-functional building for Macau Government at O1 lote in Pac On

Pengest Internacional has been awarded a contract for construction management and supervision of the Multi-functional building for Macau Government at O1 lote in Pac On, Taipa.

The building will have 10 floors and occupy an area of 3536 square meters. It will serve as a multi-functional center with parking, storage and office areas available for government usage.

pac-on-o1

 

Macau International Airport – Engineering Consultancy Services

Consultancy services to the Macau International Airport have been a great success. Renovations continue as well as new structures to improve efficiency and service.

This weeks focus project is the new firehouse. The new firehouse built next to the runway access taxiway will support the airport’s emergency dispatch. The firehouse with a reinforced concrete structure (1 storey high) was built over the water, supported by piles.

firehouse

HCSJ Substation Construction

Construction of the HCSJ Substation continues. This new substation for the Macau Electrical Company (CEM) will provide power to the improved and enlarged CSJ Hospital.

The substation will feature a concrete structure 12m high and 30m long building to house the equipment as well as 1 rolling crane.

Work started in late 2015 with Pengest Internacional providing construction management and supervision for this critical component of the CEM network.

fotorcreated