Macau LRT Station 12 Advance Works

Pengest Internacional has been chosen to provide construction supervision services to the Macau Government through the Department of Infra-structure and Transportation. Station 12 will be the first station of the light rail transit system to be built in Macau peninsula.

Station 12 will require an excavation 10 m deep and a diaphragm wall reaching bed-rock at over 30 m. It will connect the Taipa-Macau LRT line to the Barra Transport Interface.

Later the project will comprise of a tunnel linking the Sai Van Bridge and an overrun tunnel for LRT train maneuvers.

Advertisements

Main Bridge Structure Completion Macau – Zone A

On 28 Set 2017 Pengest Internacional together with other main project stakeholders celebrated the completion of the main bridge structure.

This bridge will link the peninsula of Macau to the new reclamation, Zone A also a Pengest Internacional project.

The 500m long, dual two-lane bridge is of the reinforced concrete type with post-tension tendons with 70m deep bored pile foundations.

 

 

 

Taipa Pump Station Update

Work on the new Taipa sewage pump station continues.  The work now focuses on excavation to build the structure housing the 3 pumps. 

The excavation is approximately 12 meters deep and 25 by 12 meters wide. Later in the project work will begin on the connection pipe networks, revamping and upgrading the existing network.

pump-station-1

Design Services – Welcoming New Challenges

Pengest Internacional has revamped and increased its design team. We can now offer more dedicated and improved design services to our clients. We offer a full spectrum of engineering planning, design, and construction management services, from planning and permitting through preliminary and detailed design to start-up and commissioning for all types of projects.

Our experts are skilled at leading and executing successful, multidisciplinary projects. We are experienced in the coordination of projects with strict management of quality, value, schedule and cost. Our engineering and design services range from planning and permitting through preliminary and detailed design to start-up and commissioning for all types of projects.

New Contract awarded to Pengest Internacional

Pengest is proud to announce that we have been awarded a contract for supervision and construction management for the new bridge connection Macau to Zone A reclamation.

With a history of 3 bridges successfully completed in Macau, Pengest Internacional has been yet again entrusted by the Macau Government to assist in the completion of this important project for the future development of Macau.

The project consists in 2 parallel bridges stretching over the water, linking Hac Sa Wan, Macau to the north most point of the Zone A reclamation area. The project also includes an vehicle overpass and a pedestrian underpass along the breakwater.

map

Multi-functional building for Macau Government at O1 lote in Pac On

Pengest Internacional has been awarded a contract for construction management and supervision of the Multi-functional building for Macau Government at O1 lote in Pac On, Taipa.

The building will have 10 floors and occupy an area of 3536 square meters. It will serve as a multi-functional center with parking, storage and office areas available for government usage.

pac-on-o1